Who rates, who checks
The MBE says how to rate a bridge. A state program says who rates it, who checks it, and how the result is recorded. This sheet tests one rating's checking chain against Virginia's QC and QA rules.
Key points
- A program fills the gaps the MBE leaves. The aim is that a rating comes out the same, and right, whichever office or consultant produces it.
- It has four parts. A policy (roles, qualifications, rating, posting and permit rules, QC and QA). Document control and the bridge file. Written rating procedures. The state's legal and permit vehicles.
- QC and QA are different jobs. QC runs all the time inside the rating team: checklists, an independent check of the calculations and of software results. QA is independent of the team, samples its work, and shows that the QC works.
- Someone else must check. The NBIS requires QC and QA reviews by people other than the one who produced the rating. Each rating is made by, or under the direct supervision of, a registered PE.
- FHWA checks the clock. A rating within 3 months of the initial inspection or of a change; posting within 30 days when a rating calls for it; any bridge under 3 tons closed.
IIM-S&B-86.5 is the policy; with it come guidelines G1 to G8, forms F1 to F7 and job aids J1 to J22. Under G5 the District provides the Load Rating Engineer and the QC Engineer (a PE), in house or by consultant; the QA Engineer and the Program Manager are Central Office S&B. Consultant ratings are independently reviewed and validated by the District Bridge Office before they enter VDOT's records, and that review also counts as QA. Central Office samples up to 8 structures per district each year, 75% of them rated that year. VDOT IIM-S&B-86.5 §14, §15; VDOT LR G5 pp.1–4
Quick check
On Example 1, set the QC Engineer to Person A, the engineer who did the rating. What does the sheet say?
G5 makes anyone who rated a structure ineligible for its QC or QA. The checklist records the review; it does not make a self-check independent.
Which of these is quality assurance rather than quality control?
The first two happen inside the rating team, on every rating: that is QC. Checking a sample from outside the team, to see whether the QC works, is QA.
A consultant's rating has passed the consultant's own QC. What has to happen before it goes into VDOT's system of record?
IIM-S&B-86.5 §14 requires that independent District review for every consultant rating, and counts it as the QA review.
Sources
- FHWA-NHI 130092, LRFR participant workbook, Lesson 6 (pp. 211–238).
- AASHTO MBE 3rd Ed., Article 1.4 (QC and QA), as summarised in the workbook (PW 6.23–6.25); the MBE copy in the library is protected.
- 23 CFR 650.313 (k) to (p); FHWA, Metrics for the Oversight of the National Bridge Inspection Program (2026), pp. 6, 23, 38–40 (Metrics #13 to #15).
- VDOT IIM-S&B-86.5 (June 12, 2025), §14 (QC and QA), §15 (guidelines, forms, job aids); VDOT load rating guideline G5, QC and QA (June 2025), pp. 1–4.
A study aid, not a substitute for the AASHTO MBE or an agency's rating procedures. The checking rules are as VDOT's G5 and IIM state them; examples are illustrative.